Investment Procedure
Works to be carried out | THE INVESTOR | HA THANH CONCRETE | GOVERNMENTAL ORGANIZATIONS |
Reservation of land | Investor signing land lease agreement with Ha Thanh Group | ||
Paying deposit of 30% of total land rental to Ha Thanh Group | |||
Applying for investment certificate |
Preparing necessary documents (download files) Submit to Tran De Industrial Park Management Board for appraisal and then submit to Provincial People's Committee for approval. |
Supporting the investor, when required |
Evaluated by: Provincial People’s Committee, Time: approximately 1->3 months depending on technology complication of each project |
After investment certificate is issued | Investor paying to Ha Thanh Group the 1st payment of rental | Click here to view a sample of certificate | |
Business license registration, engraving the seal | Fill in the form with the signature of investor according to Enterprise Law 2014 | Supporting the investor, when required |
Place: Soc Trang Province Industrial Park Management Board Time: 5 days. |
Signing official lease contract and land delivery | Signing the official land lease contract with Ha Thanh Group |
Land Lease Contract is notarized at authorized notary public according to regulations Time: 1 or 2 days |
|
Investor receiving land delivery from Ha Thanh Group | |||
Investor paying to Ha Thanh Group the 2nd payment of rental | |||
Dossier to apply for legal procedures in the investment preparation stage | 1/Environment impact evaluation & solution for approval |
Supporting the investor, when required |
Place: Department of Natural Resources & Environment Time: 45 days |
2/ Document for firefighting approval | Supporting the investor, when required |
Place: Police of Fire Prevention & Fight, One – door department Time: 1 week |
|
3/ Basic design dossier | |||
4/ Dossier for construction permit according to regulations (including application, basic design dossier, BVTC design dossier,...) | Place: at Soc Trang Province Industrial Park Management Board Time: 1 week |
||
Construction | Investor’s constructor signs service contracts with Ha Thanh Group for temporary supply of electricity and water during construction | According to regulations on construction management in Tran De Industrial Park issued by Tran De Industrial Park Management Board | |
Starting construction | Supporting the investor, when required. After investor determines contractor and construction cost, may entrust Ha Thanh Group to construct (free entrust fee of construction management) | ||
Investor coordinating with Ha Thanh Group for connection points of power & water supply, waste water discharge |
|||
Transfer of land use right certificate |
After the investor having paid 90% of total land rental |
Applying for transferring land use right certificate to the investors |
Handled by: Province’s Department of Natural Resources Time: about 1 month |
Investor paying to Ha Thanh Group the 3rd payment of rental | |||
Investor receiving the Land Use Right Certificate from Ha Thanh Group | Click here to view a sample of certificate | ||
Operation | Investor signing with Ha Thanh Group for service contracts of power & water supply, treatment of wastes, etc. | ||
Starting operation | Supporting the investor, when required |
Operating in accordance with the rules and regulations for secondary investors issued by the Management Board of Tran De Industrial Park |
Submitted by quantrivien on Monday, June 7, 2021 - 14:37.
Cùng chuyên mục
Group A: Attracting mainly the food processing industry and agricultural products, agricultural by-products, and agriculture in the advantages of Soc Trang province.
Group B: Attracting shipbuilding and repairing…
1. On June 12, 2020, the Prime Minister issued Decision No. 828/QD-TTg on investment policy on investment project, construction and infrastructure business of Tran De industrial park. Accordingly, Ha Thanh Concrete…
HUMAN RESOURCES
Soc Trang province has an abundant labor source, the number of population in working age until 2020, the province has over 990,000 population in working age.
PRIORITY MECHANISM
1. Corporate Income Tax…
PRIORITY MECHANISM
1. Corporate Income Tax:
- Enjoy the CIT rate of 10% for a period of 15 years;
- Tax exemption for 4 years, 50% reduction of payable tax for the next 9 years, the period of tax exemption and reduction…
Tran De - Anticipating investment attraction from the largest international deep-water port project in the Mekong Delta.
This is the gateway to open opportunities to link the Mekong Delta in particular with the Asia-…